Why can’t I get the 970 and 900 on the same day? Or 155 and 110?

These inspections are performed by separate divisions. Grading inspections must be performed first to ensure construction will be free of inundation. We are currently working on a program to permit 155 FF inspections and 110 inspections at the same time; the website will be updated when implemented.